MRL - Mark Richardson Limited is a result of the “Credit Crunch” and the down turn in the UK Construction Industry in 2009. The Company was established in November 2009. I have 25 years plus experience in the Industry, a combination of hands on site engineering through to site and project management for Major Contractors and Project Engineering/Consultation for Clients.
Monday, 28 March 2011
Monday, 7 March 2011
A3R Civils rebuild
This was meant to start right behind the de-construction.
The Longannet factor kicked in and it was well into December 2010 before the contract was awarded and the rebuild preparation work started.
The Longannet factor kicked in and it was well into December 2010 before the contract was awarded and the rebuild preparation work started.
A3R - Absorver #3 Restoration
Firstly the burnt out absorber had to be made safe before it could be demolished - or to use the PC term de-constructed.
This process took from late December 2009 until the end of August 2010.
It came in on time and on budget. A first for the FGD Project.
This process took from late December 2009 until the end of August 2010.
It came in on time and on budget. A first for the FGD Project.
Absorber #3 Fire
How do you backfill a GRP pipe?
There are two ways of doing it.
The right way, or the way it has been done here.
September 2009 February 2010 was painful to watch the guys digging out the backfilled sections and then watching it being backfilled correctly.
This time it was compacted tested and they included a thrust block, basic stuff, "lessons learned" etc.
The right way, or the way it has been done here.
September 2009 February 2010 was painful to watch the guys digging out the backfilled sections and then watching it being backfilled correctly.
This time it was compacted tested and they included a thrust block, basic stuff, "lessons learned" etc.
FGD Project
Working on the FGD Project at Scottish Power Longannet.
Flue Gas Desulphurisation Project.
Take cooling water out of the flume, pump it through 800 m of 2.8 m dia. GRP pipe put it in through an absorber mix it with the flue gass from the units. This has a chemical reaction that take the sulphate out of the flue gas.
The gas then goes back out and up the chimney, the sea water is returned to the flume in 1.8 m dia. GRP pipes where air is added in aeration beds which turns the sulphate into sulphur in sea water.
Flue Gas Desulphurisation Project.
Take cooling water out of the flume, pump it through 800 m of 2.8 m dia. GRP pipe put it in through an absorber mix it with the flue gass from the units. This has a chemical reaction that take the sulphate out of the flue gas.
The gas then goes back out and up the chimney, the sea water is returned to the flume in 1.8 m dia. GRP pipes where air is added in aeration beds which turns the sulphate into sulphur in sea water.
Mark Richardson Limited
The Company started in November 2009.
Working as an agency consultant for Scottish Power at Longannet Power Station in Kincardine.
Initially working PAYE through Search for Scottish Power.
Then formed Private Limited Company.
Moved onto working a limited company for search until April 2010.
April 2010 working direct as a contractor to Scottish Power.
Also doing a few other bits and pieces as well.
Working as an agency consultant for Scottish Power at Longannet Power Station in Kincardine.
Initially working PAYE through Search for Scottish Power.
Then formed Private Limited Company.
Moved onto working a limited company for search until April 2010.
April 2010 working direct as a contractor to Scottish Power.
Also doing a few other bits and pieces as well.